*MCR-A Topside & GBS - TURKMENISTAN

Project information

E/I works cabling                 :165,000 mt 
Topside weight                    :5,777 tons
GBS weight                          :8,030 tons
Total weight of equipments       :875 tons 
Scaffolding erected               :24,000 m3
Painting and blasting            :36,000 m2
Piping installation                 :51,000 dia-inch (800 tons)
Insulation                            :6,500 m2


            

*(Projects which founders of HICC have been involved.)